In what circumstances is the court likely to award payment to a subcontractor on the terms of “Quantum Meruit”.
- Where the subcontractor has performed its work, but part of the work contains deficiency.
- Where the subcontractor has performed extra work under a signed change order.
- Where the subcontractor has performed part of his work, but the subcontract is bankrupt.
- Where the subcontractor and the other contracting party have failed to reach the necessary agreement on matters sufficient to constitute a contract but work has already been performed.